Japan 20 m³/h Greenhouse Irrigation UF-BWRO System
Japan · Delivered and operating since 2025 · Customer and site withheld
Konche (Shenzhen) Water Treatment Technology Co., Ltd. completed equipment delivery for this greenhouse irrigation project in Japan, and the equipment was put into use in 2025. The 20 m³/h installed system combines media filtration, ultrafiltration and single-pass brackish-water RO to manage particulate fouling and dissolved salts before irrigation-water storage.
- Location
- Japan; customer and site withheld
- Application
- Brackish-water treatment for greenhouse irrigation supply
- Installed capacity
- 20 m³/h nominal RO permeate at the specified temperature
- Installed treatment train
- Coagulation support, media filtration, UF, cartridge filtration, single-pass BWRO and CIP
- Controls
- PLC and HMI with backwash, flushing, level and pressure interlocks
- Status
- Delivered and operating since 2025
Do you really need reverse osmosis for irrigation water?
RO is useful when source-water salinity or specific ions exceed the greenhouse's crop, soil or fertigation limits. The decision should be based on a complete water analysis, the irrigation target and whether blending with untreated water is acceptable.
Is reverse osmosis water good for watering plants?
RO can provide a lower-salinity base water for controlled fertigation, but the final irrigation water still needs the correct mineral balance. Crop sensitivity, soil, drainage, fertilizer program and blending strategy determine the target composition.
Is UF necessary in RO?
UF provides a consistent particulate barrier before the RO membranes when turbidity, organics or fouling risk justify it. The installed system specifies raw-water pumping and chemical support → two multimedia filters → cartridge filtration → outside-in PVDF ultrafiltration with backwash and chemical cleaning → UF-water storage → RO boosting and pH adjustment → single-pass BWRO → product-water storage.
The installed system includes 316 stainless-steel process pumps, low-pressure UPVC piping, a high-pressure stainless-steel section, PLC control, a 10-inch HMI, a membrane-cleaning loop and online product-water conductivity monitoring.
Greenhouse water-treatment selection inputs
Define the source-water analysis, seasonal temperature and salinity, daily and peak irrigation demand, crop and fertigation requirements, storage, required blending, concentrate route and the target ionic composition. These inputs determine whether media filtration alone is enough or UF is justified ahead of RO.
Plan greenhouse irrigation-water treatment.
Share the water analysis, irrigation demand, crop and fertigation targets, storage plan and concentrate route.