Home/Resources/UV FAT, SAT and Handover
UV PROCUREMENT GUIDE

Specify UV FAT, SAT and Handover Documents Before Ordering

Define what will be checked, witnessed and delivered so the acceptance basis is clear before manufacturing starts.

Review Project Requirements →
KONCHEUV PROCUREMENT GUIDEFAT · SAT · HANDOVERAGREE BEFORE ORDERRECORD CONDITIONSPUBLISHED 2026-11-24
DIRECT ANSWER

Freeze the acceptance plan and document register before manufacture.

FAT should verify contracted equipment, components, workmanship and functions under stated factory conditions. SAT should verify installation, site connections, controls and agreed operation after delivery. Neither one proves a validated UV dose unless performance verification at defined flow, UVT, lamp state and hydraulic conditions is explicitly included.

Separate FAT, SAT and performance verification

StageMain purposeTypical locationBoundary to record
FATCheck supplied equipment, workmanship, components and contracted functions before shipmentManufacturer or assembly facilityWhat can be simulated; test medium, power and instruments used
SATConfirm installation, field wiring, rotation/direction, interfaces, controls and agreed site operationProject siteWhat utilities, upstream/downstream systems and water conditions are available
Performance verificationDemonstrate the agreed treatment objective or validated operating conditionAs specified by the projectFlow, minimum UVT, lamp aging/fouling state, hydraulics, target and method
A power-on test, lamp-status check or successful alarm simulation is useful evidence. It is not automatically evidence of delivered UV dose.

Use this FAT checklist

Evidence blockChecks to agreeRecord
Identity and scopeModel, tag, quantity, nameplate, drawing revision, purchased optionsSigned scope/nameplate check
Materials and workmanshipChamber/channel components, finish, dimensions, weld and fabrication requirementsApproved drawing, BOM/material record and agreed inspection result
Pressure or leakageTest medium, pressure, hold time, visible leakage and acceptanceSigned record with actual conditions; no universal pressure should be assumed
Lamp, sleeve and ballastModel, power, wavelength/application, connector, matched ballast, sleeve and sealsComponent schedule and functional record
Instrumentation and alarmsSensor indication, setpoint, alarm text, local display and simulated faultInstrument list, alarm matrix and test result
Automatic cleaningDrive, stroke, limit feedback, sequence, override and failure responseCycle/function record when included
PLC/HMI/I/OModes, status, commands, permissives, interlocks and contracted communicationsChecked I/O list and cause/effect record
PackingPreservation, labels, loose parts, spares, shock/moisture protection where requiredPacking list and shipment photographs

Use this SAT checklist

  1. Confirm equipment tags, orientation, supports, access, drains, vents and sleeve/lamp withdrawal clearance.
  2. Confirm power supply, earthing, phase/voltage, control wiring and cable identification.
  3. Check flow direction, isolation, bypass position, channel level or reactor pressure boundary as applicable.
  4. Verify each local/remote command, status, alarm, permissive and interlock against the approved cause/effect.
  5. Verify sensor range, engineering unit, scaling, alarm delay and SCADA mapping.
  6. Run the automatic cleaning sequence and confirm limits, utilities, alarm and manual recovery when included.
  7. Record available water conditions, actual flow and any item that could not be tested.
  8. Close punch-list items with named responsibility, evidence and due date.

Open-channel control and SCADA details are covered in the open-channel UV integration guide.

Specify the handover document list

Document groupExamples to request when applicable
Approved designGeneral arrangement, P&ID, electrical schematic, control philosophy, loads and utility list
Equipment recordsNameplate/model schedule, BOM, lamp/ballast/sleeve list, instrument and valve list
Control recordsI/O list, alarm matrix, cause/effect, HMI screen list, communication/SCADA point list
Quality and testsMaterial/inspection records as contracted, pressure/leak record, calibration record, FAT/SAT and punch-list closure
Operation and maintenanceO&M manual, safe isolation, cleaning, lamp/sleeve replacement, troubleshooting and recommended spares
Delivery and sitePacking list, preservation/handling, shipment photographs, installation check, commissioning and training record

Do not assume every listed document is standard for every unit. Mark each item as required, not required or project-specific in the approved document register.

Copy this acceptance request into the RFQ

  • Equipment and options included in the FAT
  • Applicable drawings, specifications and revision status
  • Test medium, utilities, instruments and calibration evidence
  • Mechanical, pressure/leakage and electrical acceptance criteria
  • Lamp/ballast, sensor, alarm, cleaning and I/O test steps
  • Hold/witness points and remote or in-person attendance method
  • SAT responsibilities, site utilities and prerequisites
  • Performance-verification method, if required, stated separately
  • Document register with format, language, copies and due dates
  • Packing, preservation, spares, training and punch-list closure

Common buyer questions

What is the difference between UV FAT and SAT?

FAT checks the contracted equipment before shipment under factory test conditions. SAT checks installation, site connections and agreed operation after delivery. The approved plan defines the boundary.

Does a successful FAT prove the delivered UV dose?

Not automatically. Dose verification requires the agreed performance method and defined operating conditions.

When should the document list be agreed?

Before order placement, with formats, language, review stages, quantities, witness points and due dates.

Sources and limits

This checklist is a procurement aid, not a universal inspection and test plan. The approved purchase specification, drawings, document register and validation/acceptance basis control the project.

UV ACCEPTANCE PLAN

Define the tests before
manufacturing starts.

Send the project specification, required witness points, controls, document list, site conditions and performance-verification basis.