KONCHEUV PROCUREMENT GUIDEFAT · SAT · HANDOVERAGREE BEFORE ORDERRECORD CONDITIONSPUBLISHED 2026-11-24
DIRECT ANSWER
Freeze the acceptance plan and document register before manufacture.
FAT should verify contracted equipment, components, workmanship and functions under stated factory conditions. SAT should verify installation, site connections, controls and agreed operation after delivery. Neither one proves a validated UV dose unless performance verification at defined flow, UVT, lamp state and hydraulic conditions is explicitly included.
Separate FAT, SAT and performance verification
Stage
Main purpose
Typical location
Boundary to record
FAT
Check supplied equipment, workmanship, components and contracted functions before shipment
Manufacturer or assembly facility
What can be simulated; test medium, power and instruments used
SAT
Confirm installation, field wiring, rotation/direction, interfaces, controls and agreed site operation
Project site
What utilities, upstream/downstream systems and water conditions are available
Performance verification
Demonstrate the agreed treatment objective or validated operating condition
As specified by the project
Flow, minimum UVT, lamp aging/fouling state, hydraulics, target and method
A power-on test, lamp-status check or successful alarm simulation is useful evidence. It is not automatically evidence of delivered UV dose.
Packing list, preservation/handling, shipment photographs, installation check, commissioning and training record
Do not assume every listed document is standard for every unit. Mark each item as required, not required or project-specific in the approved document register.
Copy this acceptance request into the RFQ
Equipment and options included in the FAT
Applicable drawings, specifications and revision status
Test medium, utilities, instruments and calibration evidence
Mechanical, pressure/leakage and electrical acceptance criteria
Lamp/ballast, sensor, alarm, cleaning and I/O test steps
Hold/witness points and remote or in-person attendance method
SAT responsibilities, site utilities and prerequisites
Performance-verification method, if required, stated separately
Document register with format, language, copies and due dates
Packing, preservation, spares, training and punch-list closure
Common buyer questions
What is the difference between UV FAT and SAT?
FAT checks the contracted equipment before shipment under factory test conditions. SAT checks installation, site connections and agreed operation after delivery. The approved plan defines the boundary.
Does a successful FAT prove the delivered UV dose?
Not automatically. Dose verification requires the agreed performance method and defined operating conditions.
When should the document list be agreed?
Before order placement, with formats, language, review stages, quantities, witness points and due dates.
Sources and limits
This checklist is a procurement aid, not a universal inspection and test plan. The approved purchase specification, drawings, document register and validation/acceptance basis control the project.